Safety Stock Calculator

Safety stock is the buffer sized so demand does not run out during a lead time.

Safety stock

32

Reorder point
272
Buffer as a share of lead time demand
13.33%

Values update as you type. This calculator covers the single scenario its formula assumes — see Common Mistakes for what it leaves out.

The formula this calculator uses

safety stock = z x demand standard deviation x sqrt(lead time)

SS
Safety stock in units
z
Service factor, 1.645 at 95 percent and 2.326 at 99 percent
sd
Standard deviation of daily demand, in units
L
Lead time in days

How to check the result by hand

  1. 1

    Decide the service level

    Ninety five percent is the usual retail target. Go higher only where a stockout is expensive, dangerous or breaches a contract.

  2. 2

    Measure the standard deviation of daily demand

    Use the same product over a comparable period. A monthly standard deviation divided by the square root of thirty is not the same thing and will give the wrong buffer.

  3. 3

    Multiply the factor by the standard deviation

    1.645 times 8 is 13.16 units. This is the buffer that would cover a single day of lead time at the target service level.

  4. 4

    Multiply by the square root of lead time

    13.16 times the square root of six is about 32 units. Random variation accumulates as a square root, so a longer lead time needs less than proportionally more.

  5. 5

    Add it to average demand during the lead time

    Forty units a day over six days is 240, and adding 32 gives a reorder point of 272. The buffer protects the service level; the reorder point decides when to order.

For worked examples, common mistakes and the limits of this formula, read the full How To Calculate Safety Stock page.